Su Tu Den Field is located offshore Vietnam, approximately 150 km east of Vung Tau. The field is located adjacent to the Ruby field. The FPSO is installed in 48 meters water depth. First oil was achieved on October 29, 2003, approximately 18 months after contract award.
The FPSO Cuulong MV9 is a new-build FPSO with storage capacity of 1,000,000 barrels. Topside facility is provided with 65,000 bopd of oil handling capacity, 35 mmscfd of lift gas system and 82,500 bpd of water injection. The FPSO is uniquely designed so that it can be expanded in-situ to handle 110,000 bopd for Phase 2 of the project.
Scope of Work
- Engineering
- Procurement
- Construction
- Installation
- Operation and Maintenance